The first unit of Bangladesh’s Rooppur Nuclear Power Plant began supplying electricity to the national grid on 17 November 2026. The World Nuclear Association recorded the first grid connection that day. The Daily Star, citing Bangladesh Atomic Energy Commission officials, reported trial supply and plans to raise output gradually. This is Bangladesh’s first nuclear power plant.

The project and its location

Rooppur lies in Pabna district, near Ishwardi, on the banks of the Padma River. Padma is the local name for this reach of the Ganges in Bangladesh. The site is northwest of Dhaka.

The project includes two Russian-designed VVER-1200 pressurised-water reactors. The Bangladesh Atomic Energy Commission owns the plant. Nuclear Power Plant Company Bangladesh Limited is its operator. The second unit remains under construction.

Each unit has a gross rated electrical capacity of 1,200 megawatts. The two-unit project therefore has a planned gross capacity of 2,400 megawatts. Gross capacity is rated output at the generator, before subtracting the plant’s own electricity use.

How fission produces heat

In a reactor, nuclear fission splits uranium nuclei and releases energy and neutrons. Some of these neutrons cause further fission, producing a chain reaction. The reactor controls this reaction to produce heat.

Water acts as both coolant and moderator in a pressurised-water reactor. A coolant carries heat away from the fuel. A moderator slows neutrons, increasing their likelihood of causing further fission. Control rods absorb neutrons to regulate the reaction.

From reactor heat to electricity

Water in the primary circuit passes through the reactor and absorbs heat. High pressure keeps this water from boiling. It carries the heat to a steam generator, which acts as a heat exchanger.

Inside the steam generator, heat passes to water in a separate secondary circuit. This water becomes steam and drives a turbine connected to an electrical generator. The steam is then condensed into water and returned to the steam generator.

Conclusion

Rooppur’s first unit has entered grid-connected testing. Output is to rise in stages as commissioning continues, according to the reported programme.